SCHEDULE
| PROJECT KICK-OFF MEETING WITH STUDY TEAM | MAY 15, 2007 |
| DATA GATHERING | MAY–AUGUST, 2007 |
| PUBLIC INPUT MEETING TO REVIEW EXISTING CONDITIONS | SEPTEMBER 26, 2007 |
| DEVELOP RECOMMENDATION PLANS FOR STUDY TEAM REVIEW | AUGUST, 2007–MARCH, 2008 |
| SHARE PRELIMINARY RECOMMENDATIONS | APRIL 23, 2008 |
| REFINE FINAL PLAN RECOMMENDATIONS | APRIL–JUNE, 2008 |
This schedule concludes with review of final recommendations in May 2008. This process does not include any design, Right-of-Way acquisition, utility relocation or actual construction, which would need to proceed following the completion of this study.
Dates are tentative and subject to change.